28.11.2023:

The following maintenance work is planned during 2024:

  • From 13.05.2024 06:00 to 24.05.2024 16:00, the extraction service is restricted due to maintenance work.
  • From 03.06.2024 06:00 to 07.06.2024 16:00, extraction is not possible due to maintenance work.
  • From 07.10.24, 6:00 a.m. to 18.10.24, 6:00 p.m., the Wolfersberg storage facility will be completely out of operation. No injection and withdrawal is possible during this period.

09.02.2023:

The following maintenance work is planned during 2023:

– The Wolfersberg storage facility will be shut down from the 09th of October 2023, 6h00 until the 22th of October 2023, 18h00. No gas injection or withdrawal will be possible during that period.

17.01.2023:

The Wolfersberg storage facility will be shut down from January 30th 2023, 6:00 until February 03rd 2023, 20:00. No gas injection will be possible during that period.

17.09.2019:

The following maintenance work is planned during 2020:

– The Wolfersberg storage facility will be shut down from the 21th of September 2020, 6h00 until the 02th of October 2020, 18h00. No gas injection or withdrawal will be possible during that period.

08.08.2018:

The following maintenance work is planned during 2019:

– The Wolfersberg storage facility will be shut down from the 29th of April 2019, 6h00 until the 11th of May 2018, 18h00. No gas injection or withdrawal will be possible during that period.

18.08.2017:

The following maintenance work is planned during 2018:

– The Wolfersberg storage facility will be shut down from the 2nd of Juli 2018, 6h00 until the 13th of Juli 2018, 18h00. No gas injection or withdrawal will be possible during that period.

05.09.2016:

The following maintenance work is planned during 2017:

– The Wolfersberg storage facility will be shut down from the 10th of Juli 2017, 6h00 until the 21th of Juli 2017, 18h00. No gas injection or withdrawal will be possible during that period.

18.03.2016:

The annoucement made on the 28th of September 2015 is not valid anymore. Instead, the following maintenance work is planned during 2016:

– The Wolfersberg storage facility will be shut down from the 1st of June 2016, 6h00 until the 13th of June 2016, 6h00. No gas injection or withdrawal will be possible during that period.

28.09.2015:

The following maintenance work is planned during 2016:

– The Wolfersberg storage facility will be shut down from the 11th of Juli 2016, 6h00 until the 24th of Juli 2016, 18h00. No gas injection or withdrawal will be possible during that period.

04.08.2015:

The maintenance work for 2015 mentioned on the 21.07.2015 has to be extended:

– The Wolfersberg storage facility will be shut down from the 22th of Oktober 2015, 7h00 until the 01st of November 2015, 17h00. No gas injection or withdrawal will be possible during that period.

21.07.2015:

The following additional maintenance work is planned during 2015:

– The Wolfersberg storage facility will be shut down from the 26th of October 2015, 6h00 until the 30th of October 2015, 18h00. No gas injection or withdrawal will be possible during that period.

21.01.2015:

The following maintenance work is planned during 2015:

– The Wolfersberg storage facility will be shut down from the 6th of Juli 2015, 6h00 until the 18th of Juli 2015, 18h00. No gas injection or withdrawal will be possible during that period.

20.03.2014:

The following maintenance work is planned during 2014:

– The Wolfersberg storage facility will be shut down from the 7th of July 2014, 6h00 until the 18th of July 2014, 18h00. No gas injection or withdrawal will be possible during that period.